FY2025-2034 TEN YEAR PLAN PROJECT SOLICITATIONS

FY2025-2034 Ten Year Plan Project Solicitations

On March 31, 2023, NRPC submitted its final list of project priorities to NH Department of Transportation for the draft NHDOT FY 2025-2034 Ten Year Transportation Improvement Plan. View the NH DOT Ten Year Plan home page here.


NRPC has initiated the process of soliciting new projects from our municipalities for potential inclusion in the State Ten Year Transportation Improvement Plan (TYP) for the FY 2025 to 2034 period.  A project must be listed in the TYP to access state transportation funds. Potential projects can include bicycle and pedestrian improvements such as sidewalks or bike paths in addition to road and bridge improvements. This is a community’s opportunity to ensure that local transportation issues and needs are identified for funding in the TYP.

The deadline for project submissions was August 5, 2022.

Project Submissions
Click below to view full details of all the project proposals received:
2025-2034 NH Ten Year Plan Project Proposals
View TYP Project Presentations at the 9/14/2022 TTAC meeting (click "Video" to view)

Ten Year Plan Final Project List - approved at the October 12, 2022, TTAC meeting.

Project Submission Guidance
typ criteria
Nashua region projects in the 2021-2024 Transportation Improvement Program (TIP): This is included for reference as these projects are already approved and funded.
Nashua Region Metropolitan Transportation Plan (MTP):  Long-range project range project list. Review and provide updated information, if necessary.
State Ten Year Plan: NH Dept. of Transportation Ten Year Plan website. 
Statewide Project Selection Criteria: Each project is measured against the set of criteria that have been agreed upon by NHDOT and the nine New Hampshire Regional Planning Commissions. 

Project Solicitation/Selection Timeline
Project solicitation begins 6/3/2022
NRPC staff available to meet with communities to discuss projects 6/6 - 7/19/2022
Project proposals due to NRPC 8/5/2022
NRPC staff summarizes project submissions in preparation for scope/cost review 8/5 - 8/12/2022
Scope/cost review by engineering team 8/12 - 9/13/2022
Project presentations at TTAC 9/14/2022
Project scoring team reviews & scores projects 9/15 - 9/30/2022
TTAC meeting to prioritize projects 10/12/2022
NRPC finalizes projects for NHDOT review 11/4/2022
NRPC candidate projects & supporting documentation due to NHDOT 11/11/2022
NHDOT Project Engineering & Cost Review concludes 2/1/2023
TTAC recommends regional project priorities for the State TYP 3/8/2023
NRPC Commissioners finalize regional priorities for the State TYP 3/15/2023
NRPC submits priority projects to NHDOT for inclusion in the draft Ten Year Plan 3/31/2023